Follow-up of the project to renew the purification channels in the municipal area

Welcome to the site of the municipality of Oueslatia


 In the context of the follow-up of the project to renew the purification channels in the municipal area
 
and the bad condition left by the excavations that were completed on the roads,
the citizen complained and complained about the disruption of the maintenance process.
And repair roads and return them to the good condition they were in,
 
Today, Monday, March 22, 2021, at 11:30 pm, at the Municipal Palace, a working session was held under the chairmanship of Mr. Karim Maliki, Mayor and in the presence of the following gentlemen:
- Mr. Anis bin Omar, accredited Weslatia
- Mr. Abdullah Al-Ajmi, head of the processing branch
- Mr. Makram Abraham, the contractor
- Mr. Johar Bouarawi, Chairman of the Finance Committee
- Mr. Fathi Saadallah, Deputy Mayor
And the agreement was signed on the following:
- The contractor pledged to start repairing roads within the municipal area on Thursday, March 25, 2021, and in the event of violating this deadline, the Wesletia municipality will implement the law and file a complaint against it.
Noting that the weather conditions prevented the start of maintenance and repair work at an earlier date that was agreed upon with the municipality.
The municipality engineer has also been assigned to follow up and monitor the works.
 

Contact Us

Phone :77350211


Fax : 77350011

Email : commune.oueslatia@gnet.tn
 
Adress : Street Al-habib bourguiba - Oueslatia 3120

Open Hours

Monday - Thusday: 8:00 - 14:30


Friday: 8:00 - 13:30

 

Saturday - sunday : Days off